chc2 PoP (Vetta CH01)

Incident - Christchurch DC power - 07/08

Resolved

Power has been restored to all equipment within the facility.
If a device within your rack is without power, please reach out to our team who can manually intervene at no charge as required.

Problem Identified

Power is now being restored to each rack, one at a time.

Problem Identified

We expect services to be restoring in approximately 30 minutes.

Investigating

Power has been disrupted. Engineers continuing investigations.

Monitoring

Power has been restored, engineers are monitoring restoration.

Investigating

Site power has been lost.
Engineers are continuing to investigate.

Investigating

We are aware of a single power feed loss at our Vetta CH01 datacentre site.
Engineers are en-route to investigate. Updates to follow.