chc2 PoP (Vetta CH01)

Incident - Christchurch DC power - 24/08

Resolved

Incident has been resolved, we apologise for any inconvenience caused.
Further information has been gathered for our continued action plan which will progress tomorrow.

Monitoring

A power feed restored.
There was no interruption to B power feed.
Engineers remaining onsite and continuing investigations.

Investigating

Our engineer is on-site, awaiting electrical engineers.
UPS A feed has depleted.

Investigating

Mains power has currently been lost at our Vetta CH01 facility and is on battery power.
Electrical engineers have been paged and en-route due to the generator not being fully serviceable currently.
Possible loss to power feed(s) are possible, however at this stage this is a hazard notification only.