Network Switch Replacement - 220 - 11/08

Ended
Resolved

This maintenance has been completed successfully.

Began
Maintenance Planned

This work is being conducted to physically remove and replace a network switch within our 220 datacentre PoP.
During the maintenance window defined, customers can expect an outage of up to 15-20 minutes while connections are physically moved from the old switch to the new switch. This will cause impact to:

  • A single node within our voice cluster
  • A single node from within both our authoritative and recursive DNS servers
  • Web hosting services for shared, reseller & some virtual server, dedicated server & colocation customers
4 Affected Services: